Tag: Development Update

  • Overseas West Sector A Construction Status Update

    Use this briefing to check the latest construction status of Overseas West Sector A in Lahore Smart City. It covers street-by-street progress, paving work, footpath completion, and utility installation across the sector.

    Street Number 1
    On Street Number 1, crews have completed earthwork and soil filling along the road corridor. Watering and ground preparation are finished, readying the surface for tuff tile installation. Utility poles stand on one side of the street, but light fixtures have not yet been mounted. On the other side, the pedestrian footpath is still pending, with more poles and fixtures planned for later phases.

    Street Number 2
    Street Number 2 shows substantial paving progress. On the developed portion, about 80 percent of the tuff tiles have already been laid. On an unfinished patch, materials are on site and earth has been spread, but the surface still needs watering and compaction before tiles can be laid. Where paving is complete, street light poles and active fixtures are installed, and pedestrian walkways on both sides are mostly paved. However, the street is not finished across its full planned length. Only about half of the corridor, up to specific mapped plots, has been paved. The remaining stretch farther down shows no active development.

    Lane Number 16
    Lane Number 16 runs behind the plots facing the Ring Road inside Sector A. Sand and sub-base material are in place, and watering and compaction are nearly complete. Footpath paving is actively underway, with teams handling tile delivery and installation. Beyond Street Number 3 along Lane 16, tuff tiles cover most of the road surface. Only minor edge detailing and final finishing remain before that segment is complete.

    Street Number 3
    Street Number 3 displays advanced paving activity. Tuff tiles are installed on nearly 90 percent of the road surface. Crews are finishing a remaining minor segment to close the gap and connect smoothly with adjacent pathways. Workers are placing pavers by hand on the compacted base, bringing this section close to structural completion.

    Street Number 4 and Street Number 5
    Street Number 4 has an almost complete footpath framework on both sides, with only small gaps left for final tiling. Pavers are stacked nearby to finish these sections. The paved road surface includes completed tuff tiles on both sides. Still, like Street Number 2, only about 40 to 45 percent of the total street alignment is developed, leaving plots along the next section without road infrastructure. Street lighting poles have not yet been placed.

    Street Number 5 follows a nearly identical profile to Street Number 4. The main road surface in the developed section is paved, and its connection with Lane Number 16 needs only final edge alignment. Part of the pedestrian footpath still requires finishing, and light poles have not been erected. Progress on Street Number 5 is limited to roughly 40 to 45 percent of its mapped length, with no visible construction on the remaining section.

    Street Number 6 and Street Number 7
    Further into Sector A, work shifts from surfacing to foundational earthworks. On Street Number 6, initial ground leveling is done. Concrete kerb stones marking the footpath boundaries are in place on both sides. Tuff tile installation for the carriageway and walkways has not started and remains pending until paving teams and machinery move forward from earlier streets.

    On Street Number 7, heavy earthmoving equipment has completed basic ground leveling. Curbs are aligned along one side to outline the walkway, while the other side still needs curbing. Underground sewerage installation is partially incomplete along this corridor. Full surface development and tile paving on Street Number 7 will follow once foundational utilities are finished.

    Street Number 8 and Street Number 9
    Street Number 8 runs beside a designated neighborhood park. Basic leveling across the road alignment is complete, and curb stones mark the perimeter of the green space. Footpath completion and road paving are still pending. Street Number 9 is at the same stage: the surface is leveled, a curved curb line borders the open park quadrant, but roadway surfacing, footpaths on the opposite side, and electrical pole installation have not yet occurred.

    Street Number 10, Street Number 11, and Beyond
    Street Number 10 focuses on deep utility infrastructure. About 80 to 90 percent of the underground sewerage network is installed. Road leveling, curbing, and surfacing remain on hold pending final utility sign-off.

    Street Number 11 consists of raw earth mounds and initial excavation areas where digging began previously. No resurfacing, leveling, or structural paving has advanced here recently. Past Street Number 11, toward the outer perimeter plots and areas facing the Ring Road next to the executive sector, the ground remains raw and undeveloped, unchanged from previous survey periods.